Milling scale and setting bridge plug on e-line

Desafio
Controle de água
CLE.OFF.NO.10.08.V1 Milling scale and setting bridge plug on E-Line - Well Intervention - Welltec
  • Crossflow liquid rate 300-400 Sm3/d
  • Water cut Approx. 70%
  • Water cut from zone 2 Approx. 45%
  • Max. deviation 83° (@ nipple milling depth)
  • Min. restriction well 2,81" @ 10.207 ft MD
  • Max. expected SIWHP 110 bar

Background

An oil producing well completed in 2002 with eight Sliding Side Doors (SSDs), four remote and four manually operated. In March 2008, scale build-ups were observed in the well when running a PLT log. The PLT tool stopped in a remote operated sleeve for zone 3 due to scale deposits confirmed by high gamma ray readings. On a shut in pass, the PLT showed a crossflow from the lower zones (3, 4 or 5) into zone 2. During the production logging, a hole in the tubing in zone 2 was detected at 10.555 ft MD RKB (below the mechanical sleeve in zone 2) .

After this leak occurred, the pressure decreased in an adjacent well producing from the same zone and that well was considered dead due to insufficient reservoir pressure. Zone 3 was in communication with that well but there was not enough pressure support in the area to produce both wells.

Operation

The main objectives were to mill out the scale and install a retrievable plug with a flapper valve below zone 2 to avoid production from zones 3, 4 and 5. The purpose of the flapper valve was to be able to inject into these zones in case it would not be possible to remove the plug.

The second objective was to open the remote operated sleeves in zones 3 + 4 because of future plans of injecting into these zones. Due to higher time efficiency and cost effectiveness, the Well Tractor® and Well Miller® were selected to remove the scale build-up inside the wellbore. A Well Miller 212 and a Well Tractor 218 XR (Xtra Reach) were chosen to run in and open up the scale obstruction and thus provide the required final ID.

The scale was successfully removed from the well in two days. For the plug setting operation, Welltec® rigged up with the Well Tractor 218 XR, a 2,71” OD hydrostatic setting tool and a 2,65” packer with a dual flapper valve installed at the bottom. The plug was successfully installed at 11.824 ft MD. Total time for the plug setting was 4.5 hours.

Achievements

The client obtained all the objectives for the operation that was executed quickly and safely. Access to the reservoir was re-established for further operations and the operation eliminated heavy lift requirements.